| Transport and Roads |
|
Lake Road Upgrade Stage 2: (Jutland Rd to Napier Ave)
Project Update May 2009 The Lake Rd Stage Two upgrade (Jutland Rd to Napier Our contractors from Fulton Hogan are now on site, safety fencing is up, and we’re underway with the enabling works along Lake Rd. We aim to complete this part of the project before Christmas, with the road works contract scheduled to begin in early 2010 for completion late next year. North Shore City Council and Fulton Hogan very much appreciate the cooperation and understanding of businesses, residents and commuters during this works period. We will make every effort to minimise inconvenience. Give your opinion on the Hauraki Corner Plan. North Shore City Council is using the road upgrade as an opportunity to also enhance the streetscape and introduce a safety feature in front of the Hauraki Corner shops. This is partly in response to local feedback that a barrier between vehicles and pedestrians would make everyone feel safer, so we’ve looked at possible options.
Both options use bollards in areas where there is Advise which option you prefer using the following electronic form. Alternatively please email Kimdon Nguyen or phone him at 486 8600. New Signalised Pedestrian Crossing As part of the project, North Shore City
Council and the Takapuna Community
Board have resolved to locate a new
signalised pedestrian crossing on Lake
Rd just south of Harley Road. Designs revealed for Corner Plaza Of particular community interest is the creation of a
plaza/urban park (see picture) on the corner of Lake and Jutland Rds
(eastern side). As indicated by these images, this peaceful space will feature appropriate planting and street furniture to provide a pleasant area for shoppers and locals. Scheduled for completion late next year, the park will enhance this busy intersection and has been designed with easy maintenance in mind. Background Work began in March 2009 on the $8m upgrade to Lake Rd between Napier Ave and Jutland Rd – one of the busiest arterial roads in the Auckland region. The project will continue through until late 2010 to provide significant safety and traffic flow benefits to motorists, cyclists and pedestrians. Features of the project
• A safer journey for pedestrians, thanks to new footpaths and a signalised pedestrian crossing. • Two traffic lanes and one cycle lane in each direction, with each traffic lane increased to a safer width of three metres. • A new, continuous flush median to ensure turning traffic doesn’t hold up other motorists. • Indented bus bays to prevent public transport from holding up the flow of general traffic. • Undergrounding of power lines, improved stormwater infrastructure, new road surface, and landscaping features along the route. Disruption kept to a minimum During the initial ‘enabling’ works the Council and its contractor will minimise disruption to motorists by working mostly within the berm and footpath areas, not in the road. Residents and motorists will be kept informed at key stages throughout the project. A new green space to look forward to The Council has purchased land along the route, including property frontages and the restaurants on the eastern side of Hauraki Corner, to enable the improvements to be made. The restaurants have been demolished to make way for the contractor’s worksite, which will be replaced by a new pocket park once the project is completed. A two-part process The Stage Two upgrade will be handled in two steps. From now until November the contractor will clear the site and establish new property boundaries. Underground services will be relocated, including an upgrade to the water main servicing Devonport peninsula. Then a second contract will be let to undertake the road works component of the job (scheduled for December 2009 to late 2010). For further information: Please contact North Shore City Council’s Actionline on 486 8600. Questions and Answers Why does this part of Lake Rd need to be upgraded? The upgrade is essential to improve the route’s safety and efficiency. About 39,000 vehicles travel along this stretch each day. The current narrow corridor width, poor condition of the road surface and limited safe turning opportunities lead to an unacceptably high number of turning and rear-end crashes. If this is Stage Two, what was Stage One? The Stage Two project follows the successful upgrade to the Esmonde Rd/Lake Rd intersection,and is part of a suite of major transport improvements to the wider area by North Shore City Council and New Zealand Transport Agency. Image Gallery
For further information If you require further information about this project, please contact Actionline on:
|